Garage and Yard Tidy
Tidy up and burn rubbish from yard
Builders take away last of their stuff
Jamie painting house interior Overcoat
Finish trim hedge and cut long grass
Fill in gap under garage bearers over piles on two sides of garage
Fence stiles and steps
Put spouting on garage and attach to downpiping.
Make good wood storage area outside garage and move various lumber
stashes onto it
Yard all cleaned up.
Mon Feb 13
Measure up for front porch wood box and boot boxes.
Finish replacing iron sheet section in garage
Tidy up rubbish and wood by hot tub area of house. Arrange beading and
wood stored under house so easily accessible.
Stack up piles of corrugated iron and cleanup rubbish by hedge. Pickup lead
and flashing and store with iron.
Denail some pallet boards.
Unpack some kitchen boxes and Dining room packages
Tues Feb 14 - put up spouting brackets
Dad and Eb up. Get Eb to put in two stiles over railing fence, make
step for back porch while Dad and I remove old spouting brackets from
garage and lay new ones along string line
(70mm drop over 9m - probably overkill).
Fill in broken soffitt on far side of garage.
Get Eb to put corrugated iron siding around garage and dad putting in
rest of spouting brackets while I take Dads brushcutter to rest of barberry
hedge and long grass on hedge side of house.
( note to self - must get brushcutter)
Dad help Eb put new iron on house side of garage wearing my grinder
blade down from 184mm to about 40mm while cutting iron sheets. Cut
last piece with hammer and edge of my axe.
Tidy up grass piles and barberry clippings after they leave.
A whole lotta stuff done today.
Wed Feb 15
Layout seperator lines for Jamie painting Lounge - 2 tone
- dark lavender at top, lighter on bottom 2/3 of walls.
Makes rooms seem much lower.
Tidy up wood and rubbish on RHS of house, Denail old chipbd and place
in plant area
Adjust shed drainage so water not pool on topside of garage.
Go around shed and nail down shed edging over iron Dad and Eb put in
yesterday.
Place iron along back of shed and layout pieces for front between
doors and nail one section into place
Dinner in Town then to movies - "River Queen" - long turgid pointless
(a pretty typical NZ film).
Thurs Feb 16
Layout lines in Dining room for jamie to paint.
Finish yard cleanup.
Move piles round in shed, Put down big pallets and others in front of
car (2 deep) and rearrange rimu wood pile and put cardboard sheeting
down as surface.
V.V. hot day.
Over to Brendas for another load of clothing etc, empty all our stuff out of
her spare room filling car and trailer. Unload into office and spare
room, camping gear into garage.
Fri Feb 17
Placemakers truck arrive with planking, battens and spouting.
Jamie painting Dining room (second coat)
Darryl over with truck - move rubbish pile over to fire pit, douse with
petrol and set fire to it. Load house jacks onto truck
Dad arrive - We put up garage spouting and attach downpiping.
(testing shows water flows downhill in desired direction)
Install kitchen rangehood in afternoon.
Peter and Darryl back in afternoon to pickup last of their stuff and
take away their pile of griptread ( damn!)
Dad left brushcutter so cut long grass by gate (finding a fence post
and some offcuts in process) and decapitate all the docks I can find
in the paddock - in the process of doing that find a pristine offal
hole (complete with concrete cap and lid), some pallets and a 5 gallon
bucket presumably used as a honey bucket.
Shonagh tested that second phone line now working. Thank You Telecom
Sat Feb 18
Setup wood storage pallets on far side of garage. Find handle for
shonaghs gardening wagon and install that.
Move lumber from house from inside garage into neat pile on pallets.
Same for rimu sarking and beam pile under tarp in yard and move
roughsawn railings also to wood store. Cover with tarp.
Yard now cleaned up - landscaping may commence.
Line up with Brenda and Ger to dismantle the old shed/carport at end
of their property and take away. ( Dad idea but they're keen to get
rid of it).
Feb 19-20 Sun- Mon
Out to Makahu with load of pallet wood and rimu to run through
Dads planer. Came out very nicely finished. Get some wood for dad to
make boxes from sawn pile up at Dons and get some rubbish wood from
sawmill slash pile and cut to length for lining outside of Shonaghs
shade house.
Bring back another trailer load of boxes from whare.
Builders take away last of their stuff
Jamie painting house interior Overcoat
Finish trim hedge and cut long grass
Fill in gap under garage bearers over piles on two sides of garage
Fence stiles and steps
Put spouting on garage and attach to downpiping.
Make good wood storage area outside garage and move various lumber
stashes onto it
Yard all cleaned up.
Mon Feb 13
Measure up for front porch wood box and boot boxes.
Finish replacing iron sheet section in garage
Tidy up rubbish and wood by hot tub area of house. Arrange beading and
wood stored under house so easily accessible.
Stack up piles of corrugated iron and cleanup rubbish by hedge. Pickup lead
and flashing and store with iron.
Denail some pallet boards.
Unpack some kitchen boxes and Dining room packages
Tues Feb 14 - put up spouting brackets
Dad and Eb up. Get Eb to put in two stiles over railing fence, make
step for back porch while Dad and I remove old spouting brackets from
garage and lay new ones along string line
(70mm drop over 9m - probably overkill).
Fill in broken soffitt on far side of garage.
Get Eb to put corrugated iron siding around garage and dad putting in
rest of spouting brackets while I take Dads brushcutter to rest of barberry
hedge and long grass on hedge side of house.
( note to self - must get brushcutter)
Dad help Eb put new iron on house side of garage wearing my grinder
blade down from 184mm to about 40mm while cutting iron sheets. Cut
last piece with hammer and edge of my axe.
Tidy up grass piles and barberry clippings after they leave.
A whole lotta stuff done today.
Wed Feb 15
Layout seperator lines for Jamie painting Lounge - 2 tone
- dark lavender at top, lighter on bottom 2/3 of walls.
Makes rooms seem much lower.
Tidy up wood and rubbish on RHS of house, Denail old chipbd and place
in plant area
Adjust shed drainage so water not pool on topside of garage.
Go around shed and nail down shed edging over iron Dad and Eb put in
yesterday.
Place iron along back of shed and layout pieces for front between
doors and nail one section into place
Dinner in Town then to movies - "River Queen" - long turgid pointless
(a pretty typical NZ film).
Thurs Feb 16
Layout lines in Dining room for jamie to paint.
Finish yard cleanup.
Move piles round in shed, Put down big pallets and others in front of
car (2 deep) and rearrange rimu wood pile and put cardboard sheeting
down as surface.
V.V. hot day.
Over to Brendas for another load of clothing etc, empty all our stuff out of
her spare room filling car and trailer. Unload into office and spare
room, camping gear into garage.
Fri Feb 17
Placemakers truck arrive with planking, battens and spouting.
Jamie painting Dining room (second coat)
Darryl over with truck - move rubbish pile over to fire pit, douse with
petrol and set fire to it. Load house jacks onto truck
Dad arrive - We put up garage spouting and attach downpiping.
(testing shows water flows downhill in desired direction)
Install kitchen rangehood in afternoon.
Peter and Darryl back in afternoon to pickup last of their stuff and
take away their pile of griptread ( damn!)
Dad left brushcutter so cut long grass by gate (finding a fence post
and some offcuts in process) and decapitate all the docks I can find
in the paddock - in the process of doing that find a pristine offal
hole (complete with concrete cap and lid), some pallets and a 5 gallon
bucket presumably used as a honey bucket.
Shonagh tested that second phone line now working. Thank You Telecom
Sat Feb 18
Setup wood storage pallets on far side of garage. Find handle for
shonaghs gardening wagon and install that.
Move lumber from house from inside garage into neat pile on pallets.
Same for rimu sarking and beam pile under tarp in yard and move
roughsawn railings also to wood store. Cover with tarp.
Yard now cleaned up - landscaping may commence.
Line up with Brenda and Ger to dismantle the old shed/carport at end
of their property and take away. ( Dad idea but they're keen to get
rid of it).
Feb 19-20 Sun- Mon
Out to Makahu with load of pallet wood and rimu to run through
Dads planer. Came out very nicely finished. Get some wood for dad to
make boxes from sawn pile up at Dons and get some rubbish wood from
sawmill slash pile and cut to length for lining outside of Shonaghs
shade house.
Bring back another trailer load of boxes from whare.